Public Review Timeline

June 2009 Initiate Planning Initiative for AgTEC
September 30, 2009 Initial application submitted to Martin County
October – March Staff review and work with applicant
March 22, 2010 Comprehensive Plan Amendment - FINAL Submittal to Martin County
April 1, 2010 Martin County Local Planning Agency review – recommendation of APPROVAL
April 12, 2010 Martin County transmittal hearing
May 21, 2010 Treasure Coast RPC – finding of consistency
May – June 2010 State Agencies send comments to DCA
June 23, 2010 Martin County receives DCA’s ORC Report
July 2010 Martin County review and response to ORC
October 2010 Challenge filed
March 2011 DOAH Hearing
May 2011 DOAH Recommended Order
July 2011 DCA Final Order Issued, AgTEC becomes part of the Martin County Comp Plan
December 2011 Initiate Internal Planning re: SFWMD Reservation and C-23 Interconnect Canal
January 2012 Initiate coordination with SFWMD re: Reservation and C-23 Connector Canal
March 2012 Initiate PUD planning for first development envelope
March 2012 Revise and Resubmit Reservation Plan to SFWMD
May 10, 2012 Approve SFWMD Reservation for Sunrise Grove
February, 2013 Emergency PO with SFWMD for regulatory releases
July 1, 2014 Approval of Water and Sewer Agreement with City of PSL
August 1, 2014 Submit request for Martin County Pre-Application Workshop
August 21, 2014 Attend Martin County Pre-Application Workshop
November 7, 2014 Submit initial PUD Application to Martin County
December 3, 2014 Submit supplemental PUD Application materials to Martin County
January 22, 2015 Receive 1st staff report
March 19, 2015 Attend 1st staff workshop
March 23, 2015 Secure Commitment to provide high speed fiber service to the property
April 23, 2015 1st Resubmittal
June 17, 2015 Receive 2nd staff report
July 2, 2015 Attend 2nd staff workshop
October 13, 2015 2nd Resubmittal
December 23, 2015 Receive 3rd staff report
January 14, 2016 Attend 3rd staff workshop
February 18, 2016 3rd Resubmittal
April 27, 2016 Receive 4th staff report
April 29, 2016 Attend 4th staff workshop
May 4, 2016 Applicant provided itemized response to workshop
May 11, 2016 Receive “corrected” staff report
May 19, 2016 LPA public hearing/obtained revised staff comments
May 26, 2016 4th Resubmittal
June 21, 2016 BCC public hearing continued
June 22, 2016 Attend workshop with Legal staff to review new PUD language
June 27, 2016 Resubmit PUD Agreement
July 12, 2016 BCC public hearing